Belmont Construction Time Limit Ordinance:
ORDINANCE NO. 1034
AN ORDINANCE OF THE CITY OF BELMONT ESTABLISHING TIME LIMITS
FOR COMPLETION OF CONSTRUCTION AND AMENDING CHAPTER 7 OF THE
BELMONT MUNICIPAL CODE
WHEREAS, on January 8, 2008, February 12, 2008, and March 25, 2008 the
City Council, following notification in the prescribed manner, conducted public hearings,
at which hearings the Council considered public testimony and a staff report on
establishing Time Limits for Completion of Construction by amending Chapter 7 of the
Belmont Municipal Code and,
WHEREAS, the City Council did hear and use their independent judgment and
considered all said reports, recommendations and testimony herein above set forth; and,
WHEREAS, the City Council hereby adopts the staff report (dated March 25,
2008) and the facts contained therein as its own findings of fact.
SECTION 1: NOW, THEREFORE BE IT ORDAINED by the City Council of the
City of Belmont that Chapter 7 of the Belmont Municipal Code be hereby amended to
read as follows:
ARTICLE XIV. TIME LIMITS FOR COMPLETION OF CONSTRUCTION
Sec. 7-701. Purpose.
a) A continuous stream of new and ongoing construction projects within the City has
resulted in adverse impacts on its residents and businesses from the associated
construction activities. These adverse effects include: noise, loss of on-street parking,
stress on neighbors, impact on roads and other infrastructure, and a disproportionate
demand on staff time, which increases as the length of the project increases.
b) It is in the interest of the health, safety, and welfare of the citizens of Belmont to
place a reasonable time limit on the duration of each construction project, so as to
balance the needs of the owner of the project with those of his/her neighbors and the
community, for the safe and peaceful enjoyment of their properties.
Sec. 7-702. Application
a) This article shall apply to all construction, including all additions, alterations,
modifications, repairs, and improvements, which requires a building permit.
b) The time limit for completion of any building permit issued after January 1, 2002
shall be extended from the effective date of this ordinance pursuant to the time limits
specified in Section 7-703 and Section 7-704.
Sec. 7-703 Time limits for construction completion required
As part of the building permit application, a reasonable valuation must be assigned to the
project and approved by the building official. Based on that valuation, a construction time
limit, commencing on the date of issuance of the building permit, shall be established in
accordance with the table below.
Table of Time Limits
Estimated Value of Construction | Construction Time Limit(months)* |
$0 to $50,000 | 9 months |
$50,001 to $100,000 | 12 months |
$100,001 to $500,000 | 18 months |
Greater than $500,000 | 24 months |
* For landscaping work required by the Planning Commission, the applicant shall have an
additional 90 days after the date of final inspection approval of the building permit by the
Building Division for the main construction project.
Sec. 7-704 Extension
a) In the event a project has not passed a final inspection in the allotted time period
pursuant to Section 7-703, the applicant shall be entitled to a six-month extension to
complete the work. The request for an extension must be made in writing 30 days
prior to the expiration of the building permit. The extension shall be granted only if
the applicant pays a fee in the amount of one-thousand dollars ($1,000.00), and only
if an inspection by the Building Division prior to the expiration of the original permit
reveals no violations of any fire/health and safety codes at the project site.
b) In the event a project has not passed a final inspection at the expiration of the initial
six month extension, the applicant shall be entitled to no more than three additional
60 day extensions. Each extension is subject to payment of the associated fees, which
are based on the table below. Each extension is subject to an inspection by the
Building Division, prior to the expiration of the previous extension, to verify there are
no violations of fire/health and safety codes at the project site. A request for an
extension must be made in writing 30 days prior to the expiration of the building
permit.
Extension Fees
Fees for Additional Extensions | Extensions Fee |
1st 60 day extension | $1,000.00 |
2nd 60 day extension | $1,500.00 |
3rd 60 day extension | $2,000.00 |
Sec. 7-705 Construction completion
For the purpose of this article, construction shall be deemed complete upon the final
performance of all construction work, including, but not necessarily limited to, exterior
repairs and remodeling, total compliance with all conditions of application approval, and
the clearing and cleaning of all construction-related materials and debris from the site.
Final inspection and approval of the construction work by the City shall mark the date of
construction completion. Deadlines for the completions of landscaping are set forth in the
Table of Time Limits.
Section 7-706 Severability
It is hereby declared to be the intention of the City Council that the sections, paragraphs,
sentences, clauses and phrases of this Code are severable, and if any phrase, clause,
sentence, paragraph or section of this Code shall be declared unconstitutional, invalid or
unenforceable by the valid judgment or decree of any court of competent jurisdiction,
such unconstitutionality, invalidity or unenforceability shall not affect any of the
remaining phrases, clauses, sentences, paragraphs and sections of this Code.
Section 7-707 Effective Date
This Ordinance shall take effect and be in force thirty (30) calendar days after the date of
its passage.
Section 7-708 CEQA Exempt
This ordinance is categorically exempt from the provisions of Chapter 3 (commencing
with Section 21100 of Division 13 of the Public Resources Code (California
Environmental Quality Act (CEQA)) pursuant to the State CEQA Guidelines Section
15305, minor alterations and land use limitations of the CEQA Guidelines as an action
that assures the maintenance, restoration, enhancement, or protection of the environment
where the regulatory process involves procedures for protection of the environment. The
City Council further finds that adoption of this ordinance does not require review under
the California Environmental Quality Act (CEQA) because it is not a project (CEQA
Guidelines section 15378), and there is no possibility that the ordinance may have a
significant effect on the environment (CEQA Guidelines section 15061.b).
Section 7-709 Public Nuisance
Any violation of this chapter shall constitute a public nuisance and, in addition to
being subject to any other remedies allowed by law, may be abated as provided by
law.
SECTION 2:
The City Clerk shall cause this Ordinance to be published and posted in
accordance with the requirements of Section 36933 of the Government Code of the State
of California.
INTRODUCED this 25th day of March, 2008.
* * * * * * * * * * * * * *
PASSED AND ADOPTED as an Ordinance of the City of Belmont at a regular meeting
thereof held on the 8th day of April, 2008.
AYES, COUNCILMEMBERS: Braunstein, Dickenson, Feierbach, Wozniak, Lieberman
NOES, COUNCILMEMBERS: None
ABSTAIN, COUNCILMEMBERS: None
ABSENT, COUNCILMEMBERS: None
RECUSED, COUNCILMEMBERS: None
/s/ Warren Lieberman
MAYOR of the City of Belmont
ATTEST:
/s/ Terri Cook
CLERK of the City of Belmont